Vorick Group, Confidence through quality
Seniors living

Greenside Stage 2, Soldiers Point

Every electrical, communications, security and dry fire service for a seven-storey, 62-unit seniors living building.

Greenside Stage 2 under construction at Soldiers Point in April 2024, with the bowling club behind it

Photo: April 2024, during construction

Builder or client
Stevens Construction, then SNL Building, for Soldiers Point Bowling Club
Location
118 Soldiers Point Road, Soldiers Point NSW
When
2023 to November 2025
Sector
Seniors living

Greenside Stage 2 is a seven-storey building of 62 seniors living units at Soldiers Point Bowling Club. Vorick Group delivered every electrical service in it: the main switchboard, mains and submains, metering panels and distribution boards; power and lighting to every unit; data, security and CCTV, intercom and access control, MATV and dry fire; and the lift and pump room supplies, with the substation connection through our accredited partner.

The project changed builder in 2024, when SNL Building took over from Stevens Construction and carried the building through to completion. We stayed with the job across the change, so the electrical services were finished by the contractor that had started them.

Residents moved in during November 2025.

What we did

  • Main switchboard, mains and submains, metering panels and distribution boards for a seven-storey building; substation connection via our accredited partner
  • Power and lighting to every unit, data, security and CCTV, intercom and access control, MATV, dry fire, lift and pump room supplies
  • Carried through a change of builder in 2024; residents moved in November 2025

Services on this project

Commercial and retail construction, Switchboards, Security and communications, Dry fire, standby power and automation

All projects

Tendering a project?

Send the drawings and specification to estimating@vorickgroup.com, or call (02) 7233 1895.